Possible to not have completed subtasks move to new Sprint?

Randall Nicanor August 20, 2014

I have a story with multiple sub-tasks. At the end of the Sprint, half of the sub-tasks are completed and the other half are either open or in progress so when I start a new Sprint, the story and associated subtasks move to the now current Sprint. Is it possible for any subtasks with a status of closed to not move or at least show on the board under Done? Not only does it slow things down, I just want to be able to see what work is in the current sprint whether it is in Open, In Progress or Closed. Thanks.

1 answer

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 20, 2014

Sub-tasks need to stay with their parent issue, so no, because they follow their parent.