Possible to display the percent complete of related tasks to a Story?

swagner September 23, 2020

Is it possible on the Kanban cards to show completion of “related tasks” or “linked tasks” … i.e. a story would show 5/10 on the cards if 5 of the linked tasks are completed.

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 28, 2020

Hi @swagner 

There isn't anything built-in that will do that... You could build your own indicator using a custom field and the automation rule functions.  Perhaps run the rule on a scheduled trigger (every X hours) and display the custom field on your cards on the board.

Please look here are the documentation on automation rules to get started:

https://support.atlassian.com/jira-software-cloud/docs/automate-your-jira-cloud-processes-and-workflows/

Your Jira site admin should be able to help you with adding a custom field to display this value.  If that is restricted, you could put the value in a Label instead.

Best regards,

Bill