The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Portfolio planned capacity and full capacity are so far apart.

Matt Evered
October 27, 2016

I have user stories scoped by story point, aligned with teams, yet the portfolio sprint plan is only planning to 60% or less per sprint. What is keeping the plan from planning closer to 100% capacity? 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Robert Cavanna
October 28, 2016

Are you letting JIRA calculate each team's capacity, or are you setting it manually?