The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Plans - Sprint Capacity Management Requirements for Future Sprint Detail View

Eileen Mauer
October 1, 2024

When setting up the Sprint Capacity Management in Plans I am only able to see details of the future sprints if the sprint has been created in a project. We capacity plan for 6 months out and the empty future sprints clutter the sprint backlog view. Any suggestions on getting the full sprint details in the Sprint Capacity Mgmt View without creating 6 months of sprints in the backlog?

Thanks in advance!

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Анна
August 22, 2026

Hi Eileen,

Good news, this is actually a built-in feature, not something you need to work around by creating 6 months of empty sprints.

Advanced Roadmaps (Plans) has a concept called Projected sprints. These are sprints that dont exist yet in Jira, but the plan calculates and displays them based on your teams sprint duration and velocity settings. They show up in the plans timeline labeled as Projected sprint and carry capacity details just like real sprints, without you having to create anything in the backlog.

To see this working, make sure your issues are grouped by Team in the plans view settings, and that a sprint duration and velocity is set for your team in the Teams view under Plan settings. Once thats configured, the plan should automatically project sprints out as far as your timeline extends, capacity included, no manual sprint creation needed.

If you are already seeing future sprints (the ones actually created in Jira) but not projected ones beyond that, double check the teams velocity and duration settings are filled in, since projected sprints rely on those numbers to calculate.

Hope this helps!