Hey,
what is the best way to show the planned dates and actual dates in Jira? can we do this in advance road map or big picture so we can see two Gantt charts on the same page of the planned and actual situation?
Hi @Faten.Kutbi
Unfortunately, you won't be able to show them as two gantt charts in Advanced Roadmaps. You have two options: