Orphan Story assigned to a PI/Iteration, later moved to Team backlog on ART report. Automation?

Razy Kased
Contributor
November 17, 2023

Is there a way to automate that the PI is also set to unassigned once an orphan story is moved to Team backlog still being reported at the ART-level as an orphan story? I included a screenshot of the view of the user story in Jira Align which shows the unassigned backlog, this was triggered by the change of the sprint in Jira from a future sprint in the same PI to none (backlog). The issue is that Jira Align doesn't update the program increment to reflect that it is no long in PI3 and as a result is reported as an orphan story. screenshots below.

screenshotforjiraalignforumorphanstories_2nd.png

screenshotforjiraalignforumorphanstories_3rd.png

1 answer

1 accepted

1 vote
Answer accepted
Prasanth Kumar
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 2, 2024

Hi @Razy Kased 

 

There is no out of the box solution for this issue:

The workaround that we can try is:

  1. Create a custom field (Program Increment) in Jira for the issue types(User story & bugs)
  2. Once you move a user story / bug to unassigned backlog, execute a rule to set the custom field also to unassigned backlog.
  3. When the sync happens between Jira and Jira Align, the respective PI field in Jira Align will also be updated as needed.

Hope it serves your purpose?