Original estimation in the tasks ----> estimation of the story

Sari
Contributor
January 31, 2022

Hello, 

I created a list of tasks linked to a story. 

Every task has an estimation in days or hours (set in the original estimate field).

I thought that I could see then the total estimation for the story, but jira doesn't not sum up this time estimated. 

i.e.

 

Task 1 ---> original estimate: 2 days

Task 2 ---> original estimate: 1 day

Task 3 ---> original estimate: 3 hours

I would like to see in the story ----> original estimate: 3 days and 3 hours, but It is not calculated.

Is there a way to set up my board so that I can see the sum up of the estimation automatically calculated in the stories?

 

thanks a lot

2 answers

1 accepted

0 votes
Answer accepted
Jack Brickey
Community Champion
January 31, 2022

you wont see linked issues summed up. This only occurs for stories with sub-tasks.

Sari
Contributor
February 8, 2022

Ok, thank you very much for the information! @Jack Brickey 

0 votes
Shivam Nandi
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 7, 2022

hi! did you get a solution to this?

Suggest an answer