The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Original Estimates not importing if mapping Issue Type

Julia Downs
August 16, 2021

Hi there,

I'm wanting to bulk import issues to my project that contain both time estimates and issue type.

Whenever I map the issue type column in my csv to Jira 'issue type' field, after finishing the process of import, the time estimates disappear. It just shows 0.

If I don't choose to map the issue type, the time estimates remain and are displaying correctly.

Any ideas how to import both of them at the same time without Time estimates disappearing?

 

Thanks

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 16, 2021

Hi @Julia Downs 

This could be a settings issue as time tracking imports by default in units of Seconds (unless your site settings have changed.)  Please take a look at this post which includes an explanation from Atlassian staff: https://community.atlassian.com/t5/Jira-questions/How-I-can-bulk-update-quot-Original-Estimate-quot-values-from-an/qaq-p/1400622

Best regards,
Bill