The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Need help with the automation to close tickets

Adrian Criado
May 6, 2019

I want to make an automation to close the tickets in the project "Pantalla" updated to the status "Resuelta" with more than 72 hours. I've tried some options with 1 minute to try and anything works properly.Captura.PNG

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Bob
Contributor
May 6, 2019

Hi Adrian, 

It should work with updated < -72h.

Kind regards, 

Adrian Criado
May 6, 2019

I get the same results, even if i write 1 minute it only gives me a green check in project and status. 

Bob
Contributor
May 6, 2019

Hi Adrian, 

Just to be sure, you want to close issues in status Resolved that did not get an update in 72h? 

Sorry for not looking more carefully. 

I fear this won't work if you use the "Status changed" trigger (as this is an update). 

You could do this with the free add-on Automation (Lite version) with the option "Scheduled".

Alternatively you could use  Scriptrunner's Escalation Services. 

Adrian Criado
May 7, 2019

"Just to be sure, you want to close issues in status Resolved that did not get an update in 72h?" That's exactly what i want.

 

I've tried this and it works, the problem is that it closes the ticket automatically...

Captura.PNG

TAGS