The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Need help on issues that are carry forwarded to next sprint with story points

K Rahul
Contributor
March 10, 2025

 

Need help on issues that are carrt forwarded to next sprint with original estimate.

Lets assume I am starting a sprint with 2 stories. Ticket A with 6 hrs and Ticket B with 10 hrs.

By end of the sprint I have closed the  ticket A and I have logged 8 hrs of time in Ticket B but haven't closed. When I am closing the sprint, i moved the unclosed issue to next sprint.

Now in the next sprint even though user logged 8hrs in ticket B and only 2hrs of work is pending, it shows 10 hrs as original estimate, right???

How to overcome this???

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 11, 2025

Hi @K Rahul 

What problem are you trying to solve?  Knowing this will help the community offer better suggestions.

Until we know that...

Altering the Original Estimate will prevent the team from seeing the original forecasted value, reducing their ability to learn how to improve their sprint planning, estimation, and delivery in the future.

Kind regards,
Bill

0 votes
Vishal Biyani
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 10, 2025

@K Rahul 

Why do you think the original estimate will change?

The Remaining effort should show 2 hours.