The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

NOT appear the Exclusion Rule in Plan Settings

Hiroki Inoue
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 23, 2025

I want to show workitems which past more than 30 days after were completed in my plan, so I try to change the default setting but I couldn't find the exclusion rule in plan settings.

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Florian Bonniec
Community Champion
July 23, 2025

Hi

 

Go to your plan settings > Work in your plan

Select Removed work items tab, view rule in the first card, then you can define the rule.

 

Regards

Hiroki Inoue
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
July 23, 2025

tks! perfect!