No cronograma a semana inicia na segunda feira e vai até domingo, porém não trabalhamos sábado e domingo. Como retirar isso do calendario do cronograma?
Hi @Edivaldo Giacon -- Welcome to the Atlassian Community!
It is not possible to remove the weekend days from basic timeline view.
Here is a suggestion to add that feature: https://jira.atlassian.com/browse/JRACLOUD-91655
Kind regards,
Bill
Como incluo esse recurso no software?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
That feature does not exist yet. The suggestion is to add it to Jira.