My sprint scores have disappeared in the backlog

Ellie Jordan
Contributor
September 11, 2023 edited

In the backlog, usually it displays the number of points per sprint, but this seems to have disappeared. Is there a setting to get this back or is this a bug? 

Screenshot 2023-09-11 082409.png

3 answers

1 accepted

1 vote
Answer accepted
Kevin Bond
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 11, 2023 edited

Not sure if you have the same issue, but I found the same issue this morning.  I turned off "Enhance My Board and Backlog", and I can see the points now.  Hope this helps you.JIRA Settings.jpg .

(edit: adding screenshots of what changed for me)
Not sure if my issue is the same.  When I turn enhanced off, I can see the points showing at the bottom of my new sprint, and when it is on, I can no longer see them.
EnhancedOn.jpg EnhancedOff.jpg

Ellie Jordan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 12, 2023

Thank you for the tip @Kevin Bond  . I turned the enhanced board off and on again and they have reappeared on the enhanced board again too.

Sanjog Sigdel
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 12, 2023

Wow. This worked for me as well. Thanks a lot @Kevin Bond 

0 votes
Y Dang_Candylio
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 11, 2023

Hi @Ellie Jordan

 

These number are the story points at 3 types of status (Grey for To do, Blue for In progress and Green for Done). It just appears whenever the sprint is started. 

chrome_CY6NEdEI2U.png

If you want it appears in multiple sprints, you need to start these sprints (run multiple active sprints at the same time). To enable this feature in company-managed project, please go to: Settings () > Products > Under Jira Software configuration, select the toggle for Parallel sprints (remember to log in as a user with Administer Jira global permission) 

I hope this helps!

 

Regards,

Y Dang

Ellie Jordan
Contributor
September 11, 2023

Thanks for the answer but we don't want parallel sprints, we just want the total points per sprint in the backlog to show - it used to up until this morning. 

Like • 2 people like this
0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 11, 2023

Welcome to the Atlassian Community!

Could another board admin have changed the estimation statistic to a different field?

Sanjog Sigdel
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
September 11, 2023

@Nic Brough -Adaptavist-  Can you please elaborate? My backlog also don't have those estimation statistic.

Thank You

Like • Ellie Jordan likes this
Ellie Jordan
Contributor
September 11, 2023

Where would this have been changed/set and I can take a look? It is possible, but it would not have been intentional if so...

Like • 2 people like this
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 11, 2023

Board Configuration -> Estimation is the place to check.