The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
  • Community
  • Q&A
  • Jira
  • Questions
  • Multiple parallel sprints- Can be planned but not started until the completion of above active spint

Multiple parallel sprints- Can be planned but not started until the completion of above active spint

Robert Bojtos
Contributor
October 21, 2020

Hi, 

 

One of our client, up until this point could start multiple sprints on a Scrum board. 

They are unable to start a second parallel sprint on a scrum board. The start sprint button is grayed out and displays: "Can be planned but not started until the completion of above active sprint"

They said they were able to start parallel sprints on the same board up until now. I checked the board and in the productive environment it wouldn't work. I checked our test system with older data and I could start sprints just fine. 

In the meantime they closed the active sprint and started the one they wanted to start initially. Still, they want that in the future to be able to start multiple sprints. 

The option Parallel Sprints under Settings -> Applications -> Jira software configuration is enabled. The system runs on a cloud environment. 

 

Is there a way I can debug this problem and find out why a new sprint cannot be started? 

 

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Robert Bojtos
Contributor
December 14, 2020

Issue was related to custom plugin that interacted with greenhopper APIs.

It was always failing and returned an error. 

TAGS
AUG Leaders

Atlassian Community Events