if i do not complete a story and transfer it to next sprint before sprint completion as I know it will not get completed , how does that impact my sprint report? I ask this question as I would like to know if moving the story out of scope before sprint completion or moving the incomplete story after sprint completion; makes any difference to sprint report
Hi @Abhijit Sinha ,
When you click complete sprint, the system will automatically remove the unfinished Issue from the current sprint, put it back into the Backlog list or move to the next sprint.
It is recommended that you do not manually remove the Issue from the sprint. In the sprint report above, you can clearly see which Issues were removed from the sprint because they were not completed.