Dear Expert
I am new to JIRA .
I have created and uploaded the issue in company based project for scrum methodlogy.
I have found an issue while logging the work . There is only field with the name time spent is available . No other fields like Auto adjust the time , set to, and reduced to not aavailbe.
check the screenshot.
can anyone please let me where are the remaining fields or how to add or enable them on this screen .
Regards
Ghazi anwer
Welcome to the Atlassian Community!
I may be completely misunderstanding the question, but your screenshot looks like the "edit timetracking" on the main issue. Not the "log work" function.
If I am right here, then your developers are not "logging time", they are altering the estimate directly. This will show in the history, but it's not time logs.
Could you look in the "actions" menu right at the top right of the issue display and look for the "log work" action (it's usually the first entry in the menu), and ask them to try that? You can also look at the info tabs at the bottom for the "work log" tab, which should contain a "log work" link.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I said to the top right of the issue display, not the middle under the summary.
The actions menu is the other ... at the top right of your screenshot.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Ghazi Anwer ,
Welcome to the community !!
In Jira cloud, you don't have set to , reduce by etc like in Jira server
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rilwan
But when a developer logged the time , previous day time gone.
How can i see the log for that
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI @Ghazi Anwer and welcome to the community,
The time remaining is the exact field next to time spent.