Dear All,
Could you please advice what is the best way to migrate the issues from the team-managed project to the company-managed project when there are more than 4000 issues. Would it be kept the same order in the new company-managed progect. And what could be the other risks.
Many thanks.
Yulia
The only way I know to migrate issues from a team-managed project to a company-managed project is through a bulk move to the new company-managed project.
Order is probably going to be dictated by how you have your list of issues ordered from the search.
I'd make sure the workflows between the older team-managed project and the company-managed project are as identical as possible to make remapping statuses easier.
Hope this helps