The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Migrating a project from one On-Demand instance to another

JeffreyC
December 3, 2013

We currently have two On-Demand instances and would like to migrate select projects (with issues) from one instance to the other. Is it possible? If so, how so?

3 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
jason brunelle
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 5, 2014

I have the same basic questions and I would like to do so on an ongoing basis. Also, I am interested in being able to migrate the objects (screens customer fields, etc) and the configuration.

0 votes
JeffreyC
December 3, 2013

Just one time - we're migrating from our old instance to our new...

0 votes
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
December 3, 2013

Are you talking about a one time effort or is it going to be an on-going activity where you keep two projects in sync?