The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Managing sub-task in next-gen project

Cyndi Chan
Contributor
August 1, 2019

I am using Jira next-gen, and I find that sub-tasks are not visible on the Backlog view unless you drill down on the Story.  Also there doesn't appear to be a way to move just a single sub-task to a sprint.  Can someone tell me if it's possible to selectively move subtasks into a sprint?

The link to documentation on this page is wrong:  https://confluence.atlassian.com/jirasoftwarecloud/working-with-next-gen-software-projects-945104895.html

Selecting "Manage subtasks in next-gen projects" takes you to the epics page.

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Alexey Matveev
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
August 1, 2019

Hello,

It is not possible with classic boards as well. Subtasks are not visible in the backlog and if you move an issue to a sprint, then all subtasks of the issue are moved to the same sprint.