Jira Timeline - How to show Parent of the Epic and Display Multple Projects

Calvin
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 13, 2025

Hi all, we use jira cloud, and are starting to try to use the timeline feature. We are hoping to show the parent epic of the pic based on the plans hierarchy. Is this possible or is timeline Epic -> Story/Task/Bug only.

Also is plans the only alternative to show multiple projects? Its a bit iffy that Boards will have a backlog of 2 projects, but then its connected timeline does not.

1 answer

0 votes
Trudy Claspill
Community Champion
August 13, 2025

Hello @Calvin 

The Timeline option that shows as a tab along side of Board, List, Summary, etc. can show only Epics and their children. The Timeline available in a Plan, or a third party app, must be used to see the extended work item hierarchy.