The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Report no displaying when sprint is closed.

hohua.diamond
February 1, 2022

When a sprint is active I can use the reports e.g. burndown etc... However once sprint is closed then an error occurs, "The chart cannot be shown because only sub-tasks are present in this sprint, there are no parent issues."

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Answer accepted
hohua.diamond
February 9, 2022

Issue resolved: The filter used in the project removed story status = Done from sprint. Once added back into the filter. reports returned.

0 votes
Answer accepted
Pramodh M
Community Champion
February 1, 2022

Hi @hohua.diamond 

As the error says, may I know whether you are moving issues from previous sprint to current active sprint once the previous sprint is completed?

How are you managing sub-tasks? Are you only completing the sprint with sub-tasks being included in the sprint and then moving the parent issue to next sprint?

If yes this is reason

Let me know

hohua.diamond
February 1, 2022

We finish the sub-tasks within the sprint. So that the child issue (Story) is completed to gain the points.

We have many sprints and we all follow the same goal and practice, however one sprint is constantly breaking when the sprint is completed.

hohua.diamond
February 1, 2022

When I run a query based on the sprint, it returns the stories and sub-tasks.