The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Project Import - Workflows

Rahul Aich [Nagra]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 15, 2013

Hi All

As a prerequisite to project import, I am re-creating my workflows on the target jira instance. As I understand I need to re-create all workflows (transitions within it) and the workflow schemes.

My question is do I need to recreate the post-functions associated with workflow transitions as a pre-requisite in order to perform a project import?

The documentation on project import mentions nothing about post-functions.

https://confluence.atlassian.com/display/JIRA/Restoring+a+Project+from+Backup

Rahul

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 15, 2013

You mean you are recreating workflows from scratch? You should try the workflow sharing plugin or just import the workflows as XMLs.

Whatever be the case, you don't have to worry about workflow post functions if you talk purely about the import. My suggestion, however, would be to use the same workflows including post functions etc. Else it will result in a different behavior I guess?

Rahul Aich [Nagra]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 15, 2013

Thanks Jobin. Will try that.

0 votes
Robbie Martinus
April 3, 2014

Exporting workflow as XML and then importing it to target JIRA works well. It is also good to double check if everything works as expected. I found that in my case there is this one Linked Status that is not correctly set so I had to fix it manually. Post functions, conditions, workflow transitions and properties are all good.