The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Premium some initiative roll-up dates working and some not

Elaine Cawthorne
Contributor
June 19, 2024

We have Jira Premium on the cloud and I have set up a Top Level planning project which hosts the top 2 hierachy levels.  We then pull in the epics for several other projects.  I created some on the Initiatives on the plan view and some on the proect view  (may or may not bereleavant)

The issue is that on the plan basic view  some initiatives have a timeline that reflects a roll-up of all child issues and some don't!

0 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events