Apparently overnight something changed. For a couple of months I am using Jira portfolio. I had configured it in a way that the progress bars reflected the actual situation. So they contained the information (status, story points, team) of all Stories linked to the parent Epic. To reach that point I created a filter, as a source, that included all status and looks back to the updateddate even 5 years.
As from this morning it looks like I have lost all stories that are in a done state. Also Closed Features/Epics doesn't show up anymore. Is there anybody having an idea? I'm getting a bit frustraded;-((
Oops. I found out myself the solution (not the reason why it happened). I was looking at the scheduled range filter instead of the Completion Date filter. After resseting it all works well. Thank God.