The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Portfilio - Schedules not working?

Shane Burger
Contributor
April 3, 2015

Using JIRA Portfolio for Cloud

Have created a number of initiatives, epics, and assigned issues and resources to them. However, when viewing the Schedule down below, which should operate like a Gantt Chart, it is not showing a number of the Epics at all. There seems to be no rhyme or reason why one epic is shown and another is not.

Any tips and tricks? The entire "schedule" section seems very half-baked and difficult to configure in a useful manner.

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Radha Khullar
Contributor
May 18, 2015

In case the schedule shows text similar to "The current result set does not contain any stories", then you need to create teams.

Once teams are created the scheduler view starts showing data as a Gantt Chart

0 votes
Shane Burger
Contributor
May 19, 2015

Not the case. I already have teams, but still don't see the schedule working as it should.