The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results forĀ 
Search instead forĀ 
Did you mean:Ā 

Jira Plans roll-up dates in time line view

Rob Peters
Contributor
March 6, 2026

Hi Community,

We are using plans to manage all our customer projects. As you see everything is grouped by space which give a nice overview, however the timeline details are only shown once you expand a project. Since the roll-up start and due date are displayed at space level, i was wonder if there is a way to display them in the timeline. 

Thank :-)!

2026-03-06_09h08_44.png

2 answers

2 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

1 vote
Answer accepted
Marc -Devoteam-
Community Champion
March 6, 2026

Hi @Rob Peters 

No this is currently not possible, but there are feature request on this topic, you can vote for and watch.

See:

1 vote
Answer accepted
Rik de Valk _Brainboss_
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
March 6, 2026

Hi @Rob Peters , 

The Space doesn't represent a 'body of work'. Instead the Space is 'just' the workspace for a team. 

Looking at your screenshot, you have configured a level above Epic. I'll call that 'Initiative' for now. 

If you want to roll-up progress from multiple initiatives, you'll first have to define the level above Initiative. See https://support.atlassian.com/jira-cloud-administration/docs/configure-the-issue-type-hierarchy/

Once that is configured (say you call that level 'Theme'), you can create Themes, link Initiatives to these Themes, include them in your plan scope (sources of work) and see the data roll up. 

Hope that helps. 

Have a nice day!

Rik 