I am very new in jira software, so i need some help
So, question is on the summary.
Why i want to do it?
Because i want to make an automation, when the parent task is done, another paranet and its subtasks move into ToDo list from a backlog, and i want to be sure, that until all small tasks have been done, another task wouldnt start.
Community moderators have prevented the ability to post new answers.
You can do this within the workflow, using a condition.
This condition will validate all sub-tasks are closed prior to moving your story / task to the Done status. You should see a condition stating "All sub-tasks must have one of the following statuses to allow parent issue transitions: DONE"
Is this what you were looking for? I hope you find this helpful!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
There are no such options as of today.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.