The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Jira Data Center - Cluster Restart procedure

NinjawithPyjamas
July 14, 2020

I have 6 nodes in my Jira Data Center cluster ... If node 1 was to go down do i need to then stop all of the cluster nodes and bring them up one at a time or is it ok to just start up node 1 ?

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
July 18, 2020

You can start each node separately, no need to look at the others.  (That's one of the points of having a cluster - the nodes work together, but are independent of each other)