All the user stories in my current sprint have been moved to Done status. I am unable to close the sprint as JIRA is asking if the open issues should be moved to new sprint/backlog /next sprint.
For Sprints, the Board classifies Issues as "Done" based on what Statuses are in the right-hand column, not based on the Workflow.
Are the Issues all in the furthest right-hand column prior to closure?
Ste
Hi @Ste Wright
Thank you for the insight. The issue was due to the Done status not being mapped in to a column in the board.
I was able to complete the Sprint based on the your input.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This helped, thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Ashi.Lavanya welcome to the Atlassian Community!
A couple of questions:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for the insight. The issue was due to the Done status not being mapped in to a column in the board.
I was able to close the Sprint successfully.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.