When I use the JIRA issues macro in Confluence pages, I often see dates that are one day off of the date listed in JIRA.
Any ideas what could be causing this?
EDIT: As a side note, the JIRA and Confluence servers potentially reside in different time zones. I don't believe this has any bearing, though, as the date returned in the JIRA macro should be coming from JIRA.
Community moderators have prevented the ability to post new answers.
The solution I found was to add the EST time zone to the JAVA_OPTS variable in the setenv.sh file like this: -Duser.timezone=EST5EDT
Hello First off, I realize this is an old issue but I'm experiencing the same problem. Can I assume you added this solution to the setenv.sh file on the Confluence server? Or was it the Jira side? Much appreciated!