The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

JIRA Upgrade from 8.20.11 to latest LTS version Clarification

RG
Contributor
February 10, 2025

Dear Team,

We want to upgrade our JIRA 8.20.11 to the latest LTS version 10.3. Here how to proceed with our upgrade. Do we need to migrate in stages:

  1. 8.20.11 to 9.4, then 9.4 to 9.12 and then 9.12 to 10.3
  2. Or can we directly upgrade from 8.20.11 to 10.3
  3. Or can we directly upgrade it to 9.12 then 10.3
  4. Or can we upgrade it to 9.4 then 10.3

 What will happen if we directly upgrade our JIRA 8.20.11 to 10.3.

 

Please confirm.

 

2025-02-10 161255.png

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
John Funk
Community Champion
November 5, 2025

Hi RG - did you ever get this resolved? Assuming you did, and if so, what was the solution? 

0 votes
Florian Bonniec
Community Champion
February 18, 2025

Hi @RG 

 

Doing intermediate upgrade usually limit the risk of having an issue. I would do at least one intermediate in JIRA9. You can have some information in the upgrade not for the version you want to migrate too.

You also need to check with your apps if there is no intermediate version to go through that could require an intermediate version.

 

Regards