1. How can I see sprints in the roadmap? I see sprints in videos and images on the timeline but I can't find a way to get them to display in my view. See attached screen shot taken from the roadmap general instructions.
2. Can I set sprints of stories from the roadmap view?
You need to create/use a view which is grouped by Sprint (or Team).
You can also set sprints from the plan, make sure you commit the changes back to project for the changes to become applied on the stories.
Regards,
Ravi
Thanks Ravi! I also found I had set up the Roadmap as a project and not from the board. Now I can group by Team and see the sprints