JIRA: Operation -> Move is not working

Peter Beli May 16, 2019

Operations: to move a Subtask from a task to an other task is not working!

Ex.:
Task Action -> Sub-Task1 "context" to move Task Info -> Sub-Task1 "conetxt"

2 answers

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 16, 2019

You need to use "convert to issue" on the tools menu in the issue view, it's not really a "move"

Peter Beli May 17, 2019

I can not follow you ....?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 17, 2019

Look at the issue.  There is a tools option on it, with things like delete, move, clone, etc.  One option will be "convert to issue".

This is not a move in the usual sense Jira means it, it is a conversion.

0 votes
Peter Beli May 17, 2019

1. Convert to issue from sub-task to main

2. Move to another main

3. Convert again to issue from main to sub-task

Eg: Main-1/Sub-task1 -> Task1 -> Main-2/Sub-task1