Issues that are done in sprint 1 are shown in the backlogoverview of sprint 2

Johanne Fredslund Dølvik
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 17, 2022

Hi,

I am currently running a Scrum prosject with 4 sprints. I am now experiencing that issues that were marked as "Done" in Sprint 1 are shown in the backlog overview in sprint 2. Meaning it looks like all the tasks from sprint 1 are done in sprint 2. This messes up the analytics from the project. Anyone who can help me out?

 

Best, Johanne 

1 answer

1 vote
John Funk
Community Champion
January 17, 2022

Hi Johanne - Welcome to the Atlassian Community!

Is your Done status in the last column of your Scum board? Issues are not complete for the sprint unless they are in the last column, regardless of the status.

Johanne Fredslund Dølvik
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 20, 2022

Hi John! Thank you for helping me out, I finally figured it out after some Googling. The problem was as you say that the last column was something else than the Done status. 

John Funk
Community Champion
January 20, 2022

Great! Glad this is working for you now. If this answered your question, can you click on the Accept Answer button above to close this one out? Thanks!