Hi,
I am currently running a Scrum prosject with 4 sprints. I am now experiencing that issues that were marked as "Done" in Sprint 1 are shown in the backlog overview in sprint 2. Meaning it looks like all the tasks from sprint 1 are done in sprint 2. This messes up the analytics from the project. Anyone who can help me out?
Best, Johanne
Hi Johanne - Welcome to the Atlassian Community!
Is your Done status in the last column of your Scum board? Issues are not complete for the sprint unless they are in the last column, regardless of the status.
Hi John! Thank you for helping me out, I finally figured it out after some Googling. The problem was as you say that the last column was something else than the Done status.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Great! Glad this is working for you now. If this answered your question, can you click on the Accept Answer button above to close this one out? Thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.