The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Issues Are not Appearing in the Sprint.

sanam khan
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
May 2, 2023

I have tagged some issues in future sprints, but these are not visible in the assigned sprint backlog. The ticket detail screen shows the sprint assigned correctly however, the sprint backlog doesn't have the ticket listed. What could be the possible reason?

2 answers

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Trudy P Claspill
Community Champion
May 2, 2023

Hello @sanam khan 

Welcome to the Atlassian community!

In a Scrum Backlog screen the list of issues are grouped by the sprint (Active or Future) to which they are assigned. If they are not assigned to an Active or Future sprint and are not already completed then they appear at the bottom of the screen in the Backlog list.

Is the sprint to which you assigned the issues listed in the Scrum Backlog screen?

Is the issue within the scope of the filter for the board you are viewing?

Do you have any Quick Filters activated when you are viewing the Backlog?

0 votes
JM Perrot
Community Champion
May 2, 2023

Hi @sanam khan 

I think it is simply because they are in your current/future sprint. When you add an issue to a sprint, it disappears from your backlog to go to your assigned sprint.

You can also check your board filter.

TAGS