Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Issue on Velocity chart report - committed is BLANK

Sherwin Soriano
Contributor
November 11, 2025

Good day!

I would like to seek your help as to why our last 2 sprints in the Velocity Chart report are missing inputs on Committed SP.

I am not aware of any changes in our board.

When I checked the backlog insight from the backlog view, it is displaying the committed SP for current (Which I assume it is the same for the previous sprints that we have).

zero_Committed_velocity_chart_report.jpg

We are using JIRA Cloud version.

4 answers

2 votes
Alexey Pavlenko _App Developer_
Atlassian Partner
November 16, 2025

Hi @Sherwin Soriano ,

Most likely, you added scope to the sprint after it had already started. If that’s the case, you need to make sure the sprint is fully planned before it starts. Unfortunately, the Sprint Report doesn’t include a Final Scope metric. If you want to see the complete list of tasks in a sprint under a single metric, you can install the app I developed Multi-team Scrum Metrics & Retrospective.

With it, you will get the view below:

image.pngimage.png

Best regards,
Alexey

2 votes
Danut M _StonikByte_
Atlassian Partner
November 13, 2025

Hi @Sherwin Soriano,

Possible reasons for this:

  • the issues were added in sprint after the sprint was started 
  • you added SPs on the issues after the sprint was started
  • the sprint was actually started after the Sprint Planned Date/wiki

Look also at the Sprint Burndown Report for that sprint to see what happened and how the Remaining was when the sprint started. Last column indicates the Initial Commitment.

 

image.png

Also, compare this sprint start date with the start date from the Sprint report. They should be the same.

image.png

Another alternative would be to try an app (plugin) from the Atlassian Marketplace that provides a similar velocity chart. Our Great Gadgets app includes a Team Velocity gadget that may not experience this issue, as it works slightly differently from Jira’s built-in reports. In addition, it offers extra metrics such as Final Scope, which can be helpful in cases where the Initial Scope is zero.

image.png

Danut

0 votes
Iryna Komarnitska_SaaSJet_
Atlassian Partner
November 17, 2025

Hi @Sherwin Soriano ,

When Committed is blank/zero on the Velocity chart, it usually means Jira didn’t capture any estimates at the moment the sprint was started. This often happens when:

  • Issues were added to the sprint after you clicked Start sprint, or

  • Story points/estimates were added or changed after the sprint started.

I’d suggest checking the Sprint Report and issue history for those two sprints to see when the sprint field and estimates were set — that usually explains why Jira shows 0 committed even though the backlog insights look fine.

Small disclosure: I’m part of the Time in Status team.
If you need deeper sprint analytics, the Sprint Report in the Time in Status for Jira app shows:

  • committed vs completed for the last 7 sprints,

  • team workload per assignee,

  • completion rate and carryover,

  • scope change (added/removed work),
    all based on your board’s estimation method (story points, original estimate, or issue count).
    It can give a much clearer picture of why numbers look off in native Velocity and how your team actually performed in each sprint.

Frame 624636 (9).png

0 votes
sai chinamuthevi
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 11, 2025

Hi

In Jira, velocity report commitment is nothing but how many story points you have commited while starting the sprint. That means there are 10 issues in entire sprint and you have given on average 5 story points to each issue, then commitment will be 50. As i can see in screenshot can you please check if you have added any story points to assignes issues in sprint?

Velocity report will show the graphs for last 7 sprints. you can see on that specific sprint have you added the story points or not?

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events