The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is there a way to restrict who can change ranking of a JIRA in the backlog view

Richard Jones
May 6, 2015

Hi All

 

Is there a way to do this in JIRA Agile backlog view (or agile board)

 

Thanks

2 answers

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

3 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
May 6, 2015

Yup, remove the abilities for the users to Edit and/or Schedule.  You have to have both those permissions to be allowed to rank issues.

See https://confluence.atlassian.com/display/AGILE/What+are+the+permissions+used+in+Agile+Boards

2 votes
cgauterio
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
May 6, 2015

Hi Richard,

Actually, anyone that have the 'Schedule Issue' and 'Edit Issue' permissions for the issue you want to rank will be able to do that. You might have to restrict those permissions to the groups you want in order to prevent other people from ranking issues.

Cheers,

Clarissa.