Is there a way to prevent a task/subtask from being moved "in progress" by a user until a different task/subtask is marked "done" by another user?

Seth Frumkin September 21, 2016
 

1 answer

0 votes
Bob Swift
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 22, 2016

This is possible with a Conditioned validator and configuring a condition on whether or not a JQL result returns 0 or more issues. 