The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is there a way to move JIRA from a Windows to a Linux server with a newer version ?

Deleted user
January 18, 2018

trying to move from a Windows server with V6.2.6 to a Linux server with V7.5.2

should I move to the same version and then do a JIRA upgrade ?

Most docs I have found do not reference the upgrade scenario,

 

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
January 18, 2018

The docs don't really cover it because, technically, they are two separate things and trying to document them together will just confuse people.

Even if you do the actual move and upgrade in the same "window of downtime", then plan, test and consider them two separate processes.

In your case, I would migrate from a Windows 6.2.6 install to a Linux 6.2.6 install, then upgrade to 6.4, then 7.0, then 7.5.

But if it's more convenient, there's no reason not to do Windows 6.2.6 to 6.4 to 7.0 to 7.5, then migrate to Linux 7.5.  Or even do the migration part way through - Windows 6.2.6 to 6.4 to 7.0 to Linux 7.0 to 7.5.

Deleted user
January 18, 2018

Thanks Nic.

That's what I was thinking.

I will try to install v6.2.6 on my Linux server and go through the steps.