The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is there a way of adding in an additional layer above subtasks?

Jennnifer O'Brien
June 25, 2013

Hi, the way we have our Jira layed out is the top level is our Main Projects - then we have our Key Initiatives and then under that we have sub tasks. Is there a way of creating another 'layer' between the main Issue and then the sub task?

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

2 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
June 25, 2013

Not without plugins - the heirarchy in Jira is category - project - issue - subtask. That's it.

With Greenhopper, you might be able to make use of the Epic functionality, but that lives above "issue".

There are some other plugins which do some related stuff, but I think your best bet is the "structure" plugin - https://marketplace.atlassian.com/plugins/com.almworks.jira.structure