The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is there a higger issue type than an Epic, something can serve as and epic wrapper

Bernardo San Juan
October 24, 2016

Hi,

 

In our teams we create epics for any story that take longer than a sprint. So there are epics for major new features and within this epics smaller epics that are decomposed into stories. Also, these stories can at the same time be broken down into sub-tasks

The problem is that epics we can not use the "epic link" field for epics, we have to use the "link" field. Is there any new feature request to cover this?

 

Cheers

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Rob Woodgate
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 2, 2016

Hi Bernardo,

It might be worth changing the topics on your question to JIRA and jira-cloud.  This isn't really a Confluence question.  Having said that, you might find JIRA Portfolio interesting - it uses "initiatives" that can cover multiple projects and epics.