The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is it possible to update automatically the time tracking during transition workflow ?

M
April 16, 2014

Hi there,

Considering i have a 3 steps workflow.

When i create issue, i enter estimated time, foe example 10 days.

When i use the first transition, whatever is the number of days, i need to set the remaining estimation to 50%

When at last, i closed issue, the remaining is set to 0 and in time tracking i got the 100% of logged work.

Is there any postfunction to customize?

Thanks a lot for your help.

1 answer

1 accepted

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

0 votes
Answer accepted
Boris Georgiev [Appfire]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
April 16, 2014

You can use the "Set Field Value to constant or Groovy expression" (Script Runner add-on) post function for example.

M
April 17, 2014

Ok thanks, it seems to be good solution.