I can see dependencies within a project between tasks, but can i see dependencies holistically across multiple projects within my organisation ?
Hi @David Oakes and welcome to the Community!
The simple answer is yes. Dependencies are created through issue links and issue links work between any issues across Jira (as long as you have the necessary permissions in place).
On a side note - working across projects works best with company-managed projects. Team-managed projects are built with working in a single project in mind.
Hope this helps!