Is it possible to get Program increment scope change report using JIRA Atlassian?
JIRA allows us to get scope change report based on sprints. But what about in terms of feature level for a program increment?
Hi @Megha and welcome to the Community.
Can't you use fix version and releases to manage your Program Increment changes? See more here in this older but still valid article.
HTH,
KGM
@Kristján Geir Mathiesen - Currently fix versions are not useful to us in tracking this. Thank you for the inputs. As we want to make use of a date field to check on this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Megha
Trust you are well.
If you manage your Program Increments as Versions (Releases) as suggested below you can use the following Gadget to show the changes over time and more important the impact of those changes to your deliverables.
https://releasemanagement.atlassian.net/wiki/spaces/GFJR/pages/580714497/Scope+Change+Report
Hope this helps.
Kind regards,
Yuri.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Did you catch the news at Team ‘25? With Loom, Confluence, Atlassian Intelligence, & even Jira 👀, you won’t have to worry about taking meeting notes again… unless you want to. Join us to explore the beta & discover a new way to boost meeting productivity.
Register today!Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.