The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Is it possible to generate burndown chart when issue is in resolve state?

Nandani Rana
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 15, 2022

We create multiple dashboard in our project to track project status. In dashboard we want to add sprint burndown chart where

Question 1:  Can we generate burndown chart when issue ( task ) will be in resolve state?

Question 2: Can we generate burndown chart with use of original estimate time in Sprint burndown gadget?

 

 

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Champions.
November 15, 2022

Welcome to the Atlassian Community!

1.  Yes, map your "resolve" status into the last column on the board

2.  Yes, in the board settings, select "original estimate" as the sprint estimate statistic