Hi,
at first I have to say that Insights feature is great. I have only one problem, Sprint burndown chart doesn't work in the insights module. Sprint progress and epic progress work as they should. I've configured my board to estimate based on story points. Does anyone have any idea how to solve this issue?
Hi, my problem has been resolved by one of developers working on Jira Insights in Atlassian. It turned out that tasks must be estimated before start date of sprint.
Sprint Burdown Charts need story points or estimate to showcase the insights.
Have you added the story points or estimate to the issues before starting the sprint.
https://www.atlassian.com/agile/tutorials/burndown-charts
Thanks,
Pramodh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, my problem has been resolved by one of developers working on Jira Insights in Atlassian. It turned out that tasks must be estimated before start date of sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I also noticed that estimated subtasks do not count in Insights - only estimated User stories or other tickets
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.