The Atlassian Community Forums are currently in read-only mode. We will be relaunching on a new platform on September 22 (read more here). We apologize for the extended downtime. For concerns or questions, please email communitymanagers@atlassian.com. See you on the other side, on the new Atlassian Community Forums! :)

×

Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Individual Capacity/Resource Planning

Lauren Folley
February 29, 2024

I'm looking to use JIRA to do Capacity planning for team members working across different pieces of work without an additional app or integration. 

 

Goal: We have Developer 1, Developer 2, Developer 3 -- Developer 1 is a resource planned for projects A & B, Developer 2 is planned for projects A & C, Developer 3 is planned for projects B & C. 

 

I want to see where those resources line up on a timeline with the projects to know if they would be available to work on a project without having them assigned to any work.Screenshot 2024-02-29 at 10.14.01 AM.png

1 answer

Comments for this post are closed

Community moderators have prevented the ability to post new answers.

Post a new question

2 votes
Dave Rosenlund _Trundl_
Community Champion
March 1, 2024

Hi, @Lauren Folley. As far as I know, there is no way to do this natively in Jira. Except *maybe* with  Advanced Planning (aka Advanced Roadmaps).

But I don't think it's going to do what you describe, as you describe it.

So, the other alternative to look at what some of the solutions in the Atlassian Marketplace can do for you.

The fact that there are so many options to choose from (my screenscrape just shows the first six) suggests to me that you are not going to find exactly what you're looking for without one of these add-ons.

 

Screenshot 2024-03-01 at 11.58.23 AM.png

 

Good luck to you whatever you decide. Let us know what direction you chose to go in.

-dave