In manage rules, I want to end date to update automatically

Grant Crawford September 24, 2019

I have managed rules within sprints to add an automated start date when an issue is moved into a specific swim lane, I want to add a rule that adds an end date when the issue is moved to the complete swim lane, is this possible?

1 answer

1 accepted

0 votes
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 25, 2019

Hello Grant,

Welcome to Atlassian community!

Per your description, I understand that you would like to add an "End Date" field that would be automatically filed with the current time when an issue is transitioned from one status/column to the final one in a Next-gen board. Is it correct?

You can achieve it by performing the steps below:

1 - Navigate to your project > Project settings > Issue types

2 - Click on the issue types you would like to add the field > Click to create a new Date field:

Screen Shot 2019-09-25 at 17.07.03.png

3 - Navigate back to your project board > Click to create a new managed rule

4 - Configure the rule to set the field with the current time when the issue is transitioned to the final column

Screen Shot 2019-09-25 at 17.11.18.png

Let me know if this is what you were looking for.

Grant Crawford September 26, 2019

Hi Petter,

Many thanks for this, that is exactly what I was looking for.

 

Best Regards,

 

Grant.

Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
September 26, 2019

You are welcome, Grant!

Have a nice day. :)