Dear Team,
In JIRA I have created one plan, in this when I view dependencies it show reds transitions/ linking red.
For e.g.
Epic to task linking
For both epic and task Start Date- 04/01/2025 End date- 07/22/2025
Please let me reason behind that and how to should I resolve this issue.
If your dependencies display in red, that means there is a problem in your schedule. Such a problem might be that a depending task is scheduled to start before the task it depends on is completed.
That is just the theory. In order to give you better advice about your specific use case, please share a screenshot of what you are seeing.
Hope this helps!