The situation : 5 sub task for one US story => SCRUM with SPRINT
At the end of the sprint only 2 sub task are completed.
In 2016, all the sub task should follow the US Story to the next sprint
Today, is-it always the only solution ?
We need to keep the 2 completed sub task in the completed sprint to count the time which spent on.
Thank you
Community moderators have prevented the ability to post new answers.
Yes, and the concept is still nonsense.
A sprint is a set of stories that you commit to dealing with in the sprint. A story is either done, or not done. If it's not done at the end of the sprint, then it moves to the next one.
Sub-tasks are part of a story. They're "in a sprint" because they are part of the story. It's nonsense that parts of a story don't move with it, they're part of it.